Project Cost: $4,000,000 This project consists of multi-building renovation and reconstruction throughout the district. Full sidewalk replacements at the High School,Lighting upgrades, mechanical replacements, Auditorium refurbishing to include seating, lights, and stage work. New roof to the middle school, 10,000 gallon fuel oil tank removal and replacement. Security system upgrades and District wide Fiber-optic installation for the network.

Beaver River Central School District

archive

Project Cost: $2,025000 Publically Bid—Multiple Prime Contracts Complete Auditorium renovation to include: lighting, sound, rigging and seating; stage refinishing, HVAC improvements and acoustical treatments. Building renovations to include: Security systems, new domestic boilers, window and door replacements, heat exchanger replacement, roofing, masonry repair and food service equipment replacement.

Mount Markham Central Schools

offline

Project Cost: $21,500,000 Total Roof project at the High School: Masonry restoration to all four buildings; Asbestos Abatement and re-building 20 classrooms at the elementary school; Parking lot renovation at three of the buildings and site work through the district.

Starbuck Elementary Watertown City School District

inproduction

Project Cost: $4,000,000 Renovation of entire building originally built in 1953. Project included, interior updates, HVAC, Electrical, Plumbing and green technology implementation Day Light Harvesting system.

Watertown City School District

offline

Project Cost: $16,500,000 Renovations and new construction through out the entire District. Renovations included HVAC, Electrical, Plumbing, General Construction and new artificial turf stadium field. Elementary school construction included a third story, 6 classroom addition, a new cafeteria, kitchen and new food service. Renovation of an Open classroom environment into 13 new classrooms within 3 separate wings. Willey Intermediate School building won national award for Excellence in Design

Liverpool Central Schools

inproduction

Project Cost: $23,000,000 Tear off and replacement of 270,000SF of roof system; remodel of three floors of classrooms and multi-purpose rooms along with two other wings of classrooms. Installation of complete phone system throughout high school and approximately 160,000SF of drop ceiling.

Watertown City School District

inproduction

Project Cost: $400,000 Requested to stay on, bid out and complete the project for the Ohio Street school gymnasium and renovations to the school

Oswego County BOCES

inproduction

Project Cost: $500,000 Renovation to an existing building including HVAC, Electrical, Plumbing, General Construction and site work.

Watertown City School District

inproduction

Project Cost: $13,000,000 Ten classroom addition, new roof, and interior restorations. Classroom renovations at three other buildings, site work and associated asbestos abatement. 200,000 square foot new roof installation on two buildings. Complete demolition of old district offices. New traffic patterns reworked for main campus.

Marcellus Central Schools

inproduction

Project Cost: $22,900,000 Project encompassed building new bus garage with offices, mechanics bay and bus wash bay. Driver Middle School 10 classroom addition with a new gym and elevated indoor running track, new stadium with an artificial turf field with eight lane running track, lights bleachers, and press box. Interior renovations to existing school buildings, asbestos abatement of floor tiles, ceiling tiles and pipe insulation. The construction of a new concession stand/storage building for the stadium, new roads and parking lots.

Willowfield Athletic Fields Liverpool Central Schools

inproduction

Project Cost: $560,000 Supervision of two competition softball fields, one competition soccer field and two soccer practice fields, underground water systems and preparation for the second phase of the project

15 Building Installation - Liverpool Central School District

inproduction

Project Cost: $1,680,000 Supervision of Fiber Optics, Security system and partial phone system installation throughout the fifteen buildings of the school system. These systems are all-inclusive and are piggybacked on the fiber optics

Soule Road Complex Liverpool Central Schools

inproduction

Project Cost: $14,800,000 Five new additions and a total renovation to the existing building including new heating and air conditioning systems